Alia can complete an assignemnt in 5 days
and Babar can complot the same assignment
is 20 days. The time taken by both Alia and
Babar to complete the assignment working
together is:
Answers
Answer:
Let us consider Alia's work first.
Alia completes the assignment in 5 days.
=> Part of completed in first day is 1 / 5 th of the work.
Therefore work done in 1 day is 1 / 5 => Equation 1
Baber completes assignment in 20 days.
=> Part of work completed in first day is 1 / 20 th of the work.
Therefore work done in one day is 1 / 20 => Equation 2
Adding equation 1 and 2 we get the amount of work done by them in the first day, if they worked together. This implies :
1 / 5 + 1 / 20 = 1 / x
Here x represents the total number of days taken to complete the work.
Taking LCM we get,
4 / 20 + 1 / 20 = 1 / x
=> 5 / 20 = 1 / x
=> 1 / 4 = 1 / x
Cross multiplying we get,
=> 1 * x = 1 * 4
=> x = 4
Hence the total number of days that will take if Alia and Baber work together is 4 days