alice and bob can complete a work in 4 days together. if alice alone can complete the same work in 12 days , how many days can bob alone complete the work?
a) 4
b) 5
c) 6
d) 7
Answers
Answer:
c)7 days ,, pls mark me as brainliest if you are satisfied
Step-by-step explanation:
A= Alice
b=Bob
if A completes the work in 12 days, then in one day the work done is 1/12th of the total work. Let the total work be 1.
Similarly for A and B to complete 1 work, they would take 4 days and in one day, 1/4th of total work is done by both of them.
So in one day A does 1/12th of the work and B does 1/B th of the work and together they complete 1/4th of the work.
Hence, 1/B + 1/12 = 1/4
Hence B =6.
Effectively B takes 6 days to complete the work.
Given :- Alice and bob can complete a work in 4 days together. if alice alone can complete the same work in 12 days , how many days can bob alone complete the work?
a) 4
b) 5
c) 6
d) 7
Solution :-
LCM of 4 and 12 = 12 units = Let total work .
so,
→ Efficiency of (Alice + bob) = (Total work) / (Total days) = (12/4) = 3 units/day .
and,
→ Efficiency of Alice = (Total work) / (Total days) = 12/12 = 1 unit / day.
then,
→ Efficiency of bob = Efficiency of (Alice + bob) - Efficiency of Alice = 3 - 1 = 2 units/day.
therefore,
→ Time taken by bob alone = (Total work) / Efficiency = 12/2 = 6 days. (C) (Ans.)
Hence, Bob alone can complete the work in 6 days.
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371