1. Question 5.
A', 'B' and 'C' can complete a piece of work in 28 days, 32 days and 42 days respectively. 'D' is as efficient as 'A' and 'C' together. Only one person can do the work on any day, so they take daily turns to do the
work. On the first day 'C' does the work, followed by 'D', 'A' and 'B' on subsequent days; repeating this until the work is completed. In how many days will the work be completed?
1
Pick ONE option
Answers
Answered by
3
Answer:
the answer for ALL
1. Question 5.
A', 'B' and 'C' can complete a piece of work in 28 days, 32 days and 42 days respectively. 'D' is as efficient as 'A' and 'C' together. Only one person can do the work on any day, so they take daily turns to do the
work. On the first day 'C' does the work, followed by 'D', 'A' and 'B' on subsequent days; repeating this until the work is completed. In how many days will the work be completed?
1
Pick ONE option
Step-by-step explanation:
24 2/3 days
this is the answer