All project software systems do project scheduling using which procedure
(A) Time-based procedure
(B) Task-based procedure
(C) Network-based procedure
(D) Priority-based procedure​

Answers

Answered by naveentiwari7466
0

Answer:

(C) Network-based procedure

Explanation: