Alok, Kalam and Joseph individually can complete a work in
10, 12 and 15 days respectively. They started doing the work to-
gether. After 3 days Kalam had to go. Calculate in how many days
Alok and Joseph will complete the ramaining work?
Answers
Answered by
3
Answer:
45/11 is your answer please check it