Alpha Ltd., follows
Traditional costing system
and charges overheads
based on Machine hours.
Budgeted overheads are Rs.
36,00,000 and Budgeted
machine hours are 40,000.
Calculate the overhead
absorbed by product Z, if it
has consumed 6000 machine
hours for Production.
Answers
Answered by
1
Answer:
Alpha Ltd., follows
Traditional costing system
and charges overheads
based on Machine hours.
Budgeted overheads are Rs.
36,00,000 and Budgeted
machine hours are 40,000.
Calculate the overhead
absorbed by product Z, if it
has consumed 6000 machine
hours for Production.