Alternate Work
B В
A can finish a work in 15 days. B can finish the same work in
20 days. How many days would they need to finish the entire
work if they work on alternate days with B working on 1st day?
Answers
Answered by
0
Answer:
thanks for free points
Answered by
0
Step-by-step explanation:
Alternate Work
B В
A can finish a work in 15 days. B can finish the same work in
20 days. How many days would they need to finish the entire
work if they work on alternate days with B working on 1st day?