Aman, Abhishek and Albert can do a piece of work in 20 days, 30 days, and 60 days respectively. How much time will Albert take to finish the work, if he is assisted by Aman and Abhishek every 4th day. a) 40 days b)10 days c)25 days d) 45 days answer within these options
Answers
Answered by
0
Answer:
20days
Step-by-step explanation:
LCM of 20,30,60=60
so Aman does 60/20=3unit
Abhishek does 60/30=2unit
Albert does 60/60=1unit
In Four days total no of units=3(day 1)+2(day2)+1(day3)+2+1+3(4days)=12days
No.of set more required to complete work 60/12=5
5more set of 4 (5*4)=20days
Answer=20days