Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?
A) 4 days
B) 8 days
C) 3 days
D) 6 days
Answers
Answered by
7
4
Q:
Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?
A) 4 daysB) 8 daysC) 3 daysD) 6 days
Answer: D) 6 days
Explanation:
4/10 + 9/x = 1 => x = 15
Then both can do in
1/10 + 1/15 = 1/6 => 6 days
Q:
Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?
A) 4 daysB) 8 daysC) 3 daysD) 6 days
Answer: D) 6 days
Explanation:
4/10 + 9/x = 1 => x = 15
Then both can do in
1/10 + 1/15 = 1/6 => 6 days
Answered by
12
4/10 + 9/x = 1 => x = 15
Then both can do in
1/10 + 1/15 = 1/6 => 6 days
Then both can do in
1/10 + 1/15 = 1/6 => 6 days
Srishma:
bhaiya ...
Similar questions
Music,
7 months ago
Science,
7 months ago
Computer Science,
7 months ago
Environmental Sciences,
1 year ago
Social Sciences,
1 year ago
English,
1 year ago
English,
1 year ago