Math, asked by science4153, 11 months ago

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?
A) 4 days
B) 8 days
C) 3 days
D) 6 days

Answers

Answered by Anonymous
7
4

Q:

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

A) 4 daysB) 8 daysC) 3 daysD) 6 days

Answer:   D) 6 days 

Explanation:

4/10 + 9/x = 1     => x = 15 

 

Then both can do in 

1/10 + 1/15 = 1/6     => 6 days

Answered by Anonymous
12
4/10 + 9/x = 1     => x = 15 

 

Then both can do in 

1/10 + 1/15 = 1/6     => 6 days