Math, asked by eswaramoorthy3204, 9 months ago

Amit and Ananthu can do a work in 15 days and 25 days respectively. Amit started the work and left after 3 days. Ananthu took over and completed the work. In how many days was the total work completed? *​

Answers

Answered by TheLostMonk
1

23

Step-by-step explanation:

TW = LCM(15,25) = 75 units

their Efficiencies

Am = 5 u/d & An = 75/25 = 3 u /day

Am's 3 days work = 15 units

remaining w = 60 units

Ananthu completed the remaining work in 60/3= 20 days

work completed in 20+3 = 23 days