Amit can do a piece of work in 4 days and Bina can do it in 6 days. How long they will take if they work together?

Answers

Answered by Aanvigahoi
1
first find out the work done by each of them in a day

amit =1/4
bina=1/6

total work done in day if both work together= 1/4+1/6=3+2/12=5/12

no of days required to complete the work if both work together=12/5=2 2/5 days