Math, asked by kritu277, 11 months ago

Amit hires 40 man to dig the well.These men complete their work in 18 days. Amit has to get another well dug but he has only 15 days to get the digging completed.How many more men does he need to put to work? explain step by step... ​

Answers

Answered by nipungoel
2

Answer:

8

Step-by-step explanation:

days men

18 40

15 x

it is inversly proportional bcoz if men increase so day decrease

18÷15=x÷40