Amithabh can do a piece of work in 20 days and govinda can do it 30 days .they worked together to earn 500 rupees after the work was completed . what did amitabh get
Answers
Answered by
1
The LCM of 20 and 30= 60
Now,
The efficiency of Amitabh=60/20=3 and
The efficiency of Govinda=60/30=2
They together earn 500 rupees and the earning of them is decided on their efficiency.
Therefore,
Amitabh will get=500*3/5=300 rupees.