An amount of work can be completed by 24 men working 8 hours a day in 10 days. How many men with the same efficiency are required to complete the same work in 6 days, working 10 hours a day?
Answers
Answered by
4
Answer:
Step-by-step explanation:
32 men can finish the work in 6 days working 10 hrs /day
the work was finished by 24 men in 10 days working 8 hrs/day
so total men hours to complete the work= 24*10*8=1920 men hours
the men power required to finish the work in 6 days working 10 hrs/day
will be =1920/6*10=32 so 32 men can finish the work in 6 days working 10 hrs/day