an constructor made an agreement that to complete 93 km road in 20 days recruiting 250 laboured, he completed 62 km construction of the road in 10 days
a) express 3:20 in percentage
b) if 125 labours were recruited how many km of road would be constructed in 20 days
c) show that the work will be finished ahead of 5 days of the scheduled time