Math, asked by hemlatabhatta999, 1 month ago

An employee has a workforce of 300 employees to finish a project in 8 months how many extra employees should he employ to complete the project in 6 months
Answer in the question with telling as is a direct variation or indirect variation

Answers

Answered by Radhaisback2434
0

Step-by-step explanation:

If this is a construction job, look at it as man-months. 300 × 8 =2400.

X×6=2400

X=400. You will need to hire an additional 100 workers, bringing your workforce up from the original 300 to 400.

Hope its help..

Answered by Anonymous
0

Answer:

Accidents recur in a factory at the rate of 4 per week. Assume that accidents happen randomly and independently of each other. Answer the following questions to 3 places past the decimal.

a) What is the probability that there is at most 1 accident in a week?

b) What is the probability that there are 2 accidents in a week?

c) What is the probability of no accidents on a given day? Assume the factory works 7 days per week.

d) What is the probability of there being 3 accident-free days in a week?

Similar questions