an employer has a workforce of 300 employees to finishthe project in 8 months . how man y extra employees should he employ to completethe project in 6 months
Answers
Answered by
0
Answer:
400 workers will done this work in 6 months
Step-by-step explanation:
let works be x
300:8: : x:6 ( inverse proportion)
x= 300×8÷6
x= 400 workers