Math, asked by mishrashi515, 2 months ago

an employer has a workforce of 300 employees to finishthe project in 8 months . how man y extra employees should he employ to completethe project in 6 months​

Answers

Answered by avsarbansal
0

Answer:

400 workers will done this work in 6 months

Step-by-step explanation:

let works be x

300:8: : x:6 ( inverse proportion)

x= 300×8÷6

x= 400 workers