An engineer appointed 210 men to do a work in 60 days. After 12 days he appointed 70 men more to complete the work more faster. Now how many days will they take to complete the work?
Answers
Answered by
2
after 12 days
time taken by 210 men to complete remaining work=60-12=48days
time taken by 280 men to complete remaining work=48*210/280=36days
time taken by 210 men to complete remaining work=60-12=48days
time taken by 280 men to complete remaining work=48*210/280=36days