Math, asked by us180164, 9 months ago

an engineer had a workforce of 2016 persons undertook to complete a work in 10 months he was asked to complete the work in 2 months how many extra persons be needed to finish the work in 2 months​

Answers

Answered by nawal1740101
1

Answer:

8064 persons

Step-by-step explanation:

needed workforce for doing in 10 months=2016 persons

needed workforce for doing in 1 month=(2016×10) persons

needed workforce for doing in 2 months=(20160÷2) persons =10080persons

So,extra persons needed=(10080-2016)

=8064 persons