Math, asked by debdaskarmakar5869, 1 year ago

An engineer takes a project to build a road of 15 km in 300 days and employes 45 men for that .After 100 days he find only 2.5 km work is completaed find number of extra men

Answers

Answered by Mathemagic
7

45 workers working already


Let x be the total men required to finish the task in next 200 days


2.5 km done hence remaining is 12.5 km

Also, work has to be completed in next 200 days (300 - 100 = 200)


We know that, proportion of men to distance is direct proportion

and, proportion of men to days is inverse proportion


Hence, X = (45 * 12.5 * 100) / (2.5 * 200)

thus, X = 112.5 that is approximately 113


Thus, more men needed to finish the task = 113-45=68