an exploration team of 36 people completed a task in 14 days.find the number of people required to complete the work in half the number of day​

Answers

Answered by ritamriyu123
8

36×2=72

HOPE IT HELPS...MATE...

Answered by srenotanoob
8

Step-by-step explanation:

1/2 the number of days = 7

So

14 days = 36 people

7days = 36*14/7

= 72 people