Math, asked by surendarrushi31, 1 year ago

and B together finish a work piece of work in 12 days alone if a alone can finish the same work in 20 days in how many days we can complete this work A and B together finish a work in 12 days if a alone can finish the same work in completed in how many days we can complete the work

Answers

Answered by fair84
3
20×12/20-12=30

30 days

formula is a×b/a-b

20×12/20-12=30 days.


surendarrushi31: thank you for solving but can you please solve again
fair84: why u cant understand or that is wrong ans
surendarrushi31: it's correct but you please explain clearly and stepwise
fair84: ok
fair84: r u understand
surendarrushi31: thank you very much
fair84: welcome
surendarrushi31: can you solve stepwise