Anil and Mohan can do a job in 25 days. Anil alone can do
1/3
of the job in 15
days. In how many days can Mohan do it alone?
Answers
Answered by
1
Answer:
Total no. of days = 13
Step-by-step explanation:
In 3 days, Anil does 3/20 of work
Let a and s work for x days, then total work done = 3x/40
So, 3/20 + 3x/40 = 9/10
15/20 = 3x/40
X = 10
So, total no. of days = 13