anil and raju can work together to finish a work in 10 days. they together work on it for 2 days and then raju leaves. the rest of the work was done by anil alone in 30 days. in how much time can raju do the work alone?
Answers
Hope it is right
Given:
Anil and Raju can finish the work together in 10 days
They work together for 2 days
Raju leaves after 2 days and Anil does the rest of the work alone in 30 days
To find:
The time in which Raju can do the work alone
Solution:
In 1 day, the amount of work done by Anil and Raju together =
Anil and Raju have worked together for 2 days
∴ In 2 days, the amount of work done By Anil and Raju together =
∴ Remaining work to be done = ← amount of work done by Anil alone in 30 days
So,
If th of the work is done in 30 days
Then, the complete work will be done by Anil in =
Now,
The amount of work by Raju alone in 1 day is,
= [Amount of work done by Raju and Anil in 1 day] - [Amount of work done by Anil in 1 day]
Thus, Raju can do the work alone in .
-----------------------------------------------------------------------------------------
Also View:
A man takes 10 days to finish a job were as a women takes 6 days to finish a same job . together they worked for 3 days and then the women left. in how many days will the man complete the remaining work?
https://brainly.in/question/15033170
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work
https://brainly.in/question/8587762
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722