Math, asked by parokshsagar123, 2 days ago

Anil and Sunil finish a work together in 15 days. Anil alone can do thesame work in 24 days. If Sunilhas to do the work alone, how many days will he take?

Answers

Answered by bushraqadirbq10
0

Answer:

Your answer is: 24 days.