Anil can do a piece of work in 14 days which Rohit can do in 21 days they worked together for few days after which Anil left if rohit worked alone for 3 days find the total number of days it took to complete the whole work
Answers
Answer:
Step-by-step explanation:
Time taken by anil to finish the work= days.
Time taken by rohit to finish the work= days.
Anil and rohit one day work=
Anil and rohit can do the work= days.
If they are work together= days.
Work done by anil and rohit in 5.4[/tex] days work.
Remaining work=
1 work B can do in= days
work B can do in= days.
Total days to complete the work= days.
Answer:
10 1/5
Step-by-step explanation:
Given
Anil can do a piece of work in 14 days which Rohit can do in 21 days they worked together for few days after which Anil left if rohit worked alone for 3 days find the total number of days it took to complete the whole work.
Now Anil can do 1/14 of work in one day
Also Rohit can do 1/21 of work in one day
Since they worked together for few days we get
1/14 + 1/21 = 3 + 2 / 42 = 5/42 of work
Now according to question Anil left and Rohit worked alone for 3 days.
So 3 x 1/21 = 3/21 = 1/7
Now before Anil left two of them worked together for 1 – 1/7 = 6/7 of the work.
So 5/42 of work is completed together by A and B in one day
So 6/7 work will be in 6/7 / 5/42 = 6/7 x 42/5 = 36 / 5
Now Rohit worked alone for 3 days, so it will be
36/5 + 3
= 36 + 15 / 5
= 51 / 5
= 10 1/5
Therefore number of days to complete the entire work will be 10 1/5 days.