Anil
can do a piece of work in 16 days which
Shashi can finish in 24 days. If they
altermate days with Anil
starting
how many days the
be finished?
Answers
Answer:
May be 16 days
is it right.
Given :-
- Anil can do a piece of work in = 16 days.
- Shashi can finish in = 24 days.
- Anil starts the work and the work on alternate days.
To Find :-
- In how many days the work will be finished ?
Solution :-
LCM of (16 and 24) = 48 units = Let total work .
so,
→ Efficiency of Anil = (Total work) / (Total days) = 48/16 = 3 unit/day .
→ Efficiency of Shashi = (Total work) / (Total days) = 48/24 = 2 unit/day .
then,
→ In first day, Anil completes work = 3 unit .
→ In second day, Shashi completes work = 2 unit .
therefore,
→ 5 units of work completes in = 2 days .
→ 45 units of work completes in = 2 * 9 = 18 days.
so ,
→ On 19th day , it turns of Anil now and he completes = 3 units .
∴
→ In 19 days work completes = 45 + 3 = 48 units = Total work.
Hence, The work will finished in 19 days.
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371