Anil, Sunil and Rajat can complete a work in 4 hours. If Anil does the job alone in 12 hours and Sunil
in 10 hours, how long will it take for Rajat to finish the job alone?​

Attachments:

Answers

Answered by uddishcray
4

Answer:

15 hours

Explanation: