anil takes 6 days less than the time taken by varun to finidh a piece of work .if both anil and varun together ginish that work in 4days, find the time taken by vrun to finish thae work independently

Answers

Answered by abhay6122
3
certain work done
by varun is 1/x


and the work done by
Anil is 1/x-6






by given condition


4(1/x)+1/(x-6)=1




on solving it we get




x=12 or x=2


the certain work is done by varun in 12 days
and by Anil in x-6
12-6=6 days