Anjan can whitewash a house in 12 days, Arajit can do it in 10 days and Umesh can do it in 15 days. How long will it take to whitewash the house if all the three work together?
Pls Explain Step by Step​

Answers

Answered by sudiptasen3182
0

Answer:

mark me branlist please

Step-by-step explanation:

4 days

Answered by baraljigyanshu
0

If all the three will work together then it will four days