Math, asked by dhruv954042, 5 months ago

Anju can finish a work in 4 days and Manju can finish the same work in 8 days find the number of days required by Anju and Manju to finish the work if they work together​

Answers

Answered by annuverma11
0

Answer:

8/3 days means 2days 16hours