Math, asked by harshdeepharsh711, 18 days ago

Ankit and Bhanu can complete the math summer project in 10 days and 15 days respectively. They decided to work together during the vacation, but Bhanu left for a trip after some days. Then Ankit finished the remaining work in 5 days. Find the number of
days they worked together.

Answers

Answered by pratapdhruv44
0

Answer:

days they work together

Step-by-step explanation:

4 days to complete the work together

Answered by bson
1

A does work in 10 days

B does work in 15 days

A s part of work done in a day 1/10

B s part of work done in a day 1/15

A work in 5 days work done = 5/10 =1/2

remaining work =1-1/2=1/2

work done by A+B in a day

= 1/10 + 1/15 = 5/30 =1/6

A+B takes 6 days to finish the work

A+B takes 6/2 =3 days to finish 1/2 work

total no of days they worked together =3