Math, asked by appala, 10 months ago

anorge
doc
3
Paul and Lisa can do a piece of work in 40 and 60 days respectively. They began the work together, but Paul left after some days and Lisa finished the
remaining work in 40 days. After how many days did Paul leave?​

Answers

Answered by bhagyashreechowdhury
0

Given:  

Paul and Lisa can do a piece of work in 40 days and 60 days.  

Lisa completed the remaining work in 40 days  

To find:  

The number of days after which Paul left

Solution:  

In 1 day, the work done by Paul =   \frac{1}{40}

and  

In 1 day, the work done by Lisa =  \frac{1}{60}

So, in 1 day, the work done by Paul and Lisa together will be = [\frac{1}{40} + \frac{1}{60}]

Let "x" days be the no. of days after which Paul left the work .

It is given to us that after working together for "x" days, Paul leaves and Lisa completes the remaining work in 40 days.

So, we can form the equation for the whole work to be done as,  

x[\frac{1}{40} + \frac{1}{60}] + \frac{40}{60} = 1

x[\frac{3+2}{120} ] + \frac{2}{3} = 1  

⇒   x[\frac{5}{120} ] + \frac{2}{3} = 1

⇒   x[\frac{1}{24} ]  = 1 -  \frac{2}{3}

⇒   x[\frac{1}{24} ]  = \frac{3- 2}{3}

⇒   x  = \frac{1\times24}{3}

⇒   x = \bold{8 \:days}

Thus, Paul left the work after 8 days.  

-------------------------------------------------------------------------------------  

Also View:  

Bindal can finish work in 10 days jindal is twice as efficient as bindal .If they work tog-her in how many days the work will be finished?  

https://brainly.in/question/8757986  

Paul and peter can do a piece of work in 60 days, while paul can do it alone in 80 days. how many days will peter take to complete the work alone?  

https://brainly.in/question/4786032  

Similar questions