Math, asked by johnwick97, 1 month ago

answer as short as possible..
short trick if possible??? ​

Attachments:

Answers

Answered by Anonymous
2

Let, in x, y and z time A, B and C completed the work respectively

Then, one day work of A = 1/x, B = 1/y and C = 1/z

ATQ :

1/y + 1/z = 3/x ... (1)

1/x + 1/z = 4/y .... (2)

1/x + 1/y + 1/z = 1/24 .... (3)

On solving the equations :

From equation (1) and (3)

1/x + 3/x = 1/24

=> 4/x = 1/24

=> x = 24×4 = 96

So, A will complete the whole work in 96 days. ✔✔

_________________________________

Hope it helps ☺

Fóllòw Më ❤

Answered by Akshika3315
0

Step-by-step explanation:

Let time taken by B and C = x days

∴ Time taken by A = 3x days

∴ Part of work done by A, B and C in 1 day

=1x+13x=3+13x=43x∴43x=124⇒3x=4×24⇒x=4×243=32days

∴ Time taken by A = 32 × 3 = 96 days.