answer my question pls fast
Answers
Answer:
Step-by-step explanation:
Let B alone finish the work in x days.
Therefore, A alone can finish the work in (x – 6) days.
Given, (A + B) can finish the work in 4 days
x ≠ 2, ∵ if x = 2, then A alone can finish the work in = (2 – 6) = –4 days, which is not possible.
∴ x = 12, i.e. B alone can finish the work in 12 days and A alone will finish the work in 12 - 6 = 6 days
Answer:
Bhagath can finish the work in 12 days
Step-by-step explanation:
Let the number of days taken by Bhagath = X
Ram takes six days less than Bhagath = X-6
If both work together = 4 days
Then we have to find the work done in 1 day
So the equation is:
1/X + 1/X-6 = 1/4
taking common denominator
(x-6) + x/x(x-6)=1/4
x-6 +x /x^2-6x =1/4
4(x-6) + x=x^2 - 6X
4x-24+4x=x^2 - 6X
8x-24 = x^2 - 6X
x^2 - 14X + 24 =0
(X-12)(X-2) = 0
So
X=12 or X = 2
X=2 doesnt hold good for the equation hence X =12