Answer the question of the above attachment !
Class level : 10
Request: Don't spam ... I need it urgently
Answers
★ Answer
- A takes 6 days less than B to complete work.
- Both A and B can complete work in 4 days
Let B complete his work in x days.
As, One day work of B,
→ 1/x
again, As We know that A takes 6 days less than B to complete any work, One day work of A,
→ 1/(x-6)
According to Question,
→ 1/x + 1/(x-6) = 1/4
→ x-6+x/x(x-6) = ¼
→ 2x-6/x²-6x = 1/4
→ 8x-24 = x² - 6x
→ x²-6x-8x+24 = 0
→ x² - 14x + 24 = 0
→ x² -(12+2)x+24 = 0
→ x²-12x-2x + 24 = 0
→ x(x-12) -2(x-12) = 0
→ x = 12, 2
Finally, Both the values are Positive means that Both are acceptable. but if B takes 2 days to complete work then A takes Negative days to complete work. therefore we accept 12 days that B takes to complete work.
Verification:
→ 1/12 + 1/(12-6) = 1/4
→ 1/12 + 1/6 = 1/4
→ 1+2/12 = 1/4
→ 3/12 = 1/4
→ 1/4 = 1/4
Hence, B takes 12 days to complete work.
Given : A takes 6 days less than B to do the work & If both A and B working together can do it in 4 days.
To Find : Find howmany days will B to finish it ?
_________________________
Solution : Let B complete his work in x days.
- One day work of B
- A takes 6 days less than B to complete any work, One day work of A
★
Henceforth,
- Both the values are Positive means that Both are acceptable. but of B takes 2 days to complete work then A takes Negative days to complete work. we accept 12 days that B takes to complete work.
Hence,
________________________
V E R I F I C A T I O N :