Answer:
12 days
Step-by-step explanation:
Question: If 12 men working 9 hours a day can do a piece of work in 16 days, in how many days can 18 men working 8 hours a day do it?
Solution:
12 men working 9 hours a day can do it in 16 days.
12 men working 1 hour a day can complete it in: 9×16= 144 days.
1 man working 1 hour a day can complete the work in: 9×16×12= 1728 days.
18 men working 8 hours a day can complete it in:
9×16×12/8×18 = 12
Please mark as brainliest.