Math, asked by sinhanisi7, 1 day ago

answer this problem sum.

Attachments:

Answers

Answered by FatimaThePolymath
1

Answer:

12 days

Step-by-step explanation:

Question: If 12 men working 9 hours a day can do a piece of work in 16 days, in how many days can 18 men working 8 hours a day do it?

Solution:

12 men working 9 hours a day can do it in 16 days.

12 men working 1 hour a day can complete it in: 9×16= 144 days.

1 man working 1 hour a day can complete the work in: 9×16×12= 1728 days.

18 men working 8 hours a day can complete it in:

9×16×12/8×18 = 12