Gantt chart will be something like :
p1---p2---p3---p4---p2---p3---p4---p3---p4
0----4---10---16---22---28---34---40---44---49
Processes Burst time Waiting time Turn around time
1 4 0 4
2 12 16 28
3 16 28 44
4 17 32 49
Average waiting time = 19.0
Average turn around time = 31.25