Anu can complete a work in 10 days. Manu is 25% more efficient than anu and sonu is 60% more efficient than manu. Working together, how long would they take to finish the job?2 6/17 days 5 6/7 days 3 5/8 days 45/8 days
Answers
Answered by
5
Answer:
hope u find this answer helpful☺
Attachments:
Answered by
3
First option is correct.
Step-by-step explanation:
Since we have given that
Number of days in which Anu can complete her work = 10 days
Since Manu is 25% more efficient than Anu.
So, Number of days in which Manu can complete her work would be
Since Sonu is 60% efficient than Manu.
So, Number of days in which Sonu can complete his work would be
So, working together , it will take to finish the job would be
Hence, it will take days to finish the job.
Therefore, First option is correct.
# learn more:
Anu can do 1/5of a work in 5 days and
Sonu can do 2/3 of the work in 8 days.In how
many days can both Anu and sonu together the
work
https://brainly.in/question/13151886
Similar questions