ap----》arithmetic progression
Attachments:
Answers
Answered by
0
Answer:
Rs. 27,750
Step-by-step explanation:
Arranging the given question in sequence;
200, 250, 300,
t1=a=200
t2=250
t3=300
d=?
t30=b=?
S30=?
Now,
d= t2-t1 = 250-200 = 50
t30 = a+29d = 200 + 29*50 = 200 + 1450 = 1650
S30 = (n/2)(a+b) = (30/2)(200+1650) = 15*1850 = 27750
∴The contractor has to pay Rs.27,750 if he has delayed the work for 30 days.