Math, asked by kami8683, 1 year ago

Aptitude ques a petrol bunk needs 56 men to fill 20000 litres in 72 days. how many men are needed to fill 30000 litres in 63 days

Answers

Answered by aquialaska
3

Answer:

42 men required to do the work.

Step-by-step explanation:

Given:

56 men fill 20000 liters in 72 days.

To find: Number of men required to fill 30000 liters in 63 days.

We know that if M_1 persons can do W_1 work in D_1 days and M_2 persons can do W_2 work in D_2 days. then,

M_1\:W_1\:D_1=M_2\:W_2\:D_2

let x be the require number of men.

So,

56\times20000\times72=x\times30000\times63

80640000=1890000x

x = 42

Therefore, 42 men required to do the work.

Answered by SuryaKumarArun
1

Answer:

96 men required to do the work.

Step-by-step explanation:

56 men need to fill 20000 litres in 72 days

means:

1 man can fill = 20000/56 litres in 72 days

1 man can fill = (20000/56)*(1/72) litres in 1 day

then:

x men can fill 30000 litres in 63 days

x*(20000/56)*(1/72)*63 = 30000

x = 96 litres

Similar questions