Aptitude ques a petrol bunk needs 56 men to fill 20000 litres in 72 days. how many men are needed to fill 30000 litres in 63 days
Answers
Answered by
3
Answer:
42 men required to do the work.
Step-by-step explanation:
Given:
56 men fill 20000 liters in 72 days.
To find: Number of men required to fill 30000 liters in 63 days.
We know that if persons can do work in days and persons can do work in days. then,
let x be the require number of men.
So,
x = 42
Therefore, 42 men required to do the work.
Answered by
1
Answer:
96 men required to do the work.
Step-by-step explanation:
56 men need to fill 20000 litres in 72 days
means:
1 man can fill = 20000/56 litres in 72 days
1 man can fill = (20000/56)*(1/72) litres in 1 day
then:
x men can fill 30000 litres in 63 days
x*(20000/56)*(1/72)*63 = 30000
x = 96 litres