Math, asked by babyaliya544, 1 year ago

Ariun can complete a project in 20 days and Aryan can do it in 25 days. They start
working together but due to some reason Arjun leaves the project after 2 days. In
how many days will the project be completed?​

Answers

Answered by suhaswaghhhhh
0

may be 18 days....... ...

Answered by sushantaboserem
0

Answer: 2*(1/20+1/25) +x/25 =1

x = the days Aryan reQd. , total dvys reQd. =x+2 =..............

Step-by-step explanation: