Math, asked by stewart5240, 10 months ago

arjun takes 6 days less than aman to finish a piece of work .if both of them together can finish the work in 4 days,in how many days aman alone can finish the work

Answers

Answered by rishu1192
1

Step-by-step explanation:

aman takes 5 days to complete alone