Arun and amit can do a piece of work in 9 days and 12 days respectively.If they work alternate days and amit starts the work first then in how many days 35/36 parts of whole work will be completed
Answers
Answered by
5
Step-by-step explanation:
As per the given data,
If they work alternately then work done by Arun & Amit in 2 days = 1/9 + 1/12 = 7/36
Work done in 5 pair of days = 5 × 7/36 = 35/36
∴ They require 5 pair of days i.e, 10 days to complete 35/36 parts of whole work
Similar questions