2

Given : Arun completes 1/3 rd of a piece of work alone in 7/12th time taken by Roy to complete entire work alone.  Together can complete the work in 28 days,

To find :  in  how many days Arun working alone can complete the work

Solution:

Let say  Roy can complete the work alone in 12 D   Days

7/12th time taken by Roy to complete entire work alone  = (7/12)12D = 7D  days

Arun completes 1/3 rd of a piece of work alone  in 7D  Days

=> Arun completes  work alone in 7D/(1/3)  = 21D  Days

Roy 1 day work = 1/12D

Arun 1 Day work = 1/21D

Their total 1 Days work  =  1/12D  + 1/21D

= (7 + 4) /84D

= 11 /84D

11 /84D    =  1/28

=> 11 = 3D

=> D = 11/3

Arun working alone can complete the work  = 21D  = 21 * 11 /3

=  77 Days

Arun working alone can complete the work  in 77 Days

Learn more:

with P starting the work, working on alternate days P and Q can ...

https://brainly.in/question/12303996

24 men working 8 hours a day finish work in 10 days how many men ...

https://brainly.in/question/7520445

A and B can do a piece of work in 12 days; A,B and C all working ...

https://brainly.in/question/7839397

Similar questions