Math, asked by salonirajaput98, 7 months ago

ASSESSMENT
None of these
A completes a work in 15 days. B complete the same work in 20 days. A started working alone after 1 days B joined him. How many day will they now take together to
complete the remaining work?
07
08
06​

Answers

Answered by anubala771777
0

Answer:

6 is the answer

Step-by-step explanation:

mark me brilliant

follow me

Similar questions