Assume that we have information on an old process plant that has the
capacity to produce 10 gallons/day of a particular chemical. The cost
today to build the plant would be Rs.1, 000. The appropriate cost factor for this type of plant is 0.5. An order-of-magnitude estimate of the cost is required for a plant with a capacity of 30gallons/day.
Answers
Answered by
0
Explanation:
old process plant that has the
capacity to produce 10 gallons/day of a particular chemical. The cost
today to build the plant would be Rs.1, 000. The appropriate cost factor for this type of plant is 0.5. An order-of-magnitude estimate of the cost is required for a plant with a capacity of 30gallons/day.