Business Studies, asked by divithakur1, 4 months ago

Assume that we have information on an old process plant that has the
capacity to produce 10 gallons/day of a particular chemical. The cost
today to build the plant would be Rs.1, 000. The appropriate cost factor for this type of plant is 0.5. An order-of-magnitude estimate of the cost is required for a plant with a capacity of 30gallons/day.​

Answers

Answered by vikasaradhyabn851
0

Explanation:

old process plant that has the

capacity to produce 10 gallons/day of a particular chemical. The cost

today to build the plant would be Rs.1, 000. The appropriate cost factor for this type of plant is 0.5. An order-of-magnitude estimate of the cost is required for a plant with a capacity of 30gallons/day.

Similar questions