At the time of Asiad games, a contractor who had a workforce of 560 men undertook to complete a portion of stadium in 9 months. He was asked to complete his job in 7 months. How many extra men should be employed to finish the job?
Answers
Answered by
0
Answer:
560 divide by 9 and then multiply it by 7