At which phase of the project life cycle is monitoring most important and why

Answers

Answered by susan017a
1

Answer:

Although it is sequenced as the 4th stage in the project management life cycle, the monitoring phase is in fact implemented most often DURING the execution stage, not afterwards. While the team executes the plan, PMs begin to monitor and control project work, to ensure progression is on track with the schedule.

HOPE THIS HELPS......

#FOLLOW ME...