Athulith can complete a piece of work in 36 days while
Bipin can do it in 45 days. If they work together, how
long will they take to complete the work?​

Answers

Answered by Anonymous
5

Answer:

Athulit 1 day' s work =1/36

Bipin's 1 day's work=1/45

----------------------------------

Their 1 day's work=1/36+1/45

=5+4/180=9/180=1/20

Ans: They together can finish the work in 20 days